Progress Video April 09

1) Guardrail Installation




2) Site overview

- Progress Photo - Apr 09


22/4/09 - Toll Plaza Canopy




21/4/09 - Laying and compacting Asphaltic Concrete Wearing Course (ACWC)

21/4/09 - Laying and compacting Asphaltic Concrete Binder Course (ACBC)



21/4/09 - Tack coat spraying to Dense Bituminous McAdam (DBM)

21/4/09 - DBM Coring Test




16/4/09 - Guard rail installed



20/4/09 - Installation of aircond completed


16/4/09 - Installation of guardrail in progress



16/4/09 - Toll Plaza roof installation almost completed





15/4/09 - Toll booth installation in progress





14/4/09 - Toll gantry completed





12/4/09 - 3m Length Transition Slab Installation on the Top of Box Culvert


12/4/09 - Turfing at Verge and Slope Area.










11/4/09 - Concreting Works for Drainage (Slope Drain, Shoulder Drain and Toe Drain)









11/4/09 - Aluminium Strip Ceiling, Aluminium Fascia and (MRI Colourtile) Interlocking Tiles Installations for Toll Canopy.




4/4/09 - Stainless Steel Gutter Installation



3/4/09 - Concreting Works for Box Culvert Wing Wall

Weekly Report Apr09

Weekly Report No. 16

Weekly Report No. 15






Weekly Report No. 14



Weekly Report No. 13

Progress Video March09




1) 1st Concrete Pavement Concreting in progress



2) Toll Booth Island




3) Steel Truss




4) Steel Truss Installation

- Progress Photo - Mar09

28/3/09 - Installation of steel truss



28/3/09 - Excavation for toe drain in progress

27/3/09 - Concreting NJB in progress







26/3/09 - Connecting new fiber optic cable



21/3/09 - Concreting Works for Box Culvert up to Finished Level (Night Work).













20/3/09 - Concreting Works for 3 Nos. of Toll Islands (Night Work).








20/3/09 - Steel trusses welding work in progress












19/3/09 - M&E piping ready for toll booth island.












19/3/09 - Box culvert reinforcement bar erection in progress.







17/3/09 - Transition slab concreting in progress.












12/3/09 - BRC fixing for concrete pavement.











12/3/09 - Water proofing membrane installation in progress.











10/3/09 - Concreting for the 1st concrete pavement in progress (night work).



10/3/09 - Fibre optic cable installation in progress (not urinate!).







6/3/09 - Concreting work for 300 mm x 300 mm box culvert at Toll Booth area.






5/3/09 - Concreting Box Culvert Extension Wall






4/3/09 - M&E Works for Generator Services.


















PRE-CONSTRUCTION VIDEO



24/12/08: Video - Before Construction Works

.
.
MAIN PAGE
.
.
.
.
.
..

Weekly Report Mar09

Weekly Report No. 12

Weekly Report No. 11

Weekly Report No. 10


.



.




Weekly Report No. 9

Progress Video until Feb09

Click on the video title below to watch the video. If the video cannot be opened, please request your IT DEPT to give you access to YOUTUBE.
.




1 - Backfilling work





2 - Concreting work for pad footing




3 - Piling work for box culvert






4 - Hacking concrete pavement - 17/2/09




5 - Fixing swipe post - 19/2/09








6 - Swipe post concreting - 19/2/09




7 - Box culvert - nightwork - 19/2/09





8 - Removing old highmast - 25/2/09



9 - Installation of new highmast - 25/2/09 (MUST SEE)

Weekly Report Feb09

Weekly Report No. 8

Weekly Report No. 7





Weekly Report No. 6









Weekly Report No. 5