Click to enlarge..
.
.

 27/2/09 - Laying new highmast cable replacing old cable.

 26/2/09 - Box culvert base concreting in progress - nightwork.

 26/2/09 - Column concreting final level.

26/2/09 - Both highmast completed.

 26/2/09 - Installation of Highmast in progress.

 25/2/09 - New highmast installation in progress
.jpg)
25/2/09 - Removing old highmast.

 19/2/09 - Box culvert - night work

19/2/09 - Concreting swipe post base in progress.
.jpg)
 19/2/09 - Fixing swipe post in progress.
.jpg)
 17/2/09 - Box culvert area - fixing formwork and river diversion using pipe.

 14/2/09 - Construct M&E Manhole.

 14/2/09 - Hacked existing concrete pavement for construction joint.

13/2/09 - Concreting works for 4 nos. of columns upto 2m height column casing.

 13/2/09 - Divert river flow due to Box Culvert Extension works.

12/2/09 - Installed 2 Nos of ducts for Fibre Optic and Telecommunication Cables.
 
 

 12/2/09 - Concreting works
- 800mm depth of Concrete Barriers 
- Base for M&E Service Pit
- 2 Nos. of sumps at Pipe Culvert

 11/2/09 - Cut existing concrete pavement due to the next Toll Island construction stages.

 11/2/09 - Installed Swipe Post accordingly at the center of concrete barrier formwork.

 10/2/09 - Formwork and rebar installation for Service Pit (M&E Works) including with 4 Nos. of GI Pipes attached at the both sides.
10/2/09 - Rebar Installation for Concrete Barrier at Toll Island.
7/2/09 - Laid 50 mm and 75mm lean concrete at service pit and concrete barrier area.

 7/2/09 - Hacked existing wing wall which is obstruct piling works near box culvert opening.

 6/2/09 - Relocated temporary 2 Nos. of street lighting due to subbase backfilling

 6/2/09 - Backfilling and recompact subgrade at footing area.

 5/2/09 - Carry out PDA Test to the pile at box culvert area.

 2/2/09: Reinforcement work for Toll Plaza column in progress.
3/2/09: Box culvert: Setting out piling work. 

3/2/09: Fixing pvc rain water down pipe to the column.

3/2/09: Fixing the concrete casing as formwork.

4/2/09: Column concreting in progress.

 4/2/09: Piling work at the box culvert area started.