- Progress Photo - Feb09

Click to enlarge..
.
.
27/2/09 - Laying new highmast cable replacing old cable.

26/2/09 - Box culvert base concreting in progress - nightwork.



26/2/09 - Column concreting final level.


26/2/09 - Both highmast completed.



26/2/09 - Installation of Highmast in progress.




25/2/09 - New highmast installation in progress







25/2/09 - Removing old highmast.






19/2/09 - Box culvert - night work







19/2/09 - Concreting swipe post base in progress.






19/2/09 - Fixing swipe post in progress.






17/2/09 - Box culvert area - fixing formwork and river diversion using pipe.



14/2/09 - Construct M&E Manhole.






14/2/09 - Hacked existing concrete pavement for construction joint.






13/2/09 - Concreting works for 4 nos. of columns upto 2m height column casing.




13/2/09 - Divert river flow due to Box Culvert Extension works.





12/2/09 - Installed 2 Nos of ducts for Fibre Optic and Telecommunication Cables.



12/2/09 - Concreting works

- 800mm depth of Concrete Barriers


- Base for M&E Service Pit


- 2 Nos. of sumps at Pipe Culvert






11/2/09 - Cut existing concrete pavement due to the next Toll Island construction stages.



11/2/09 - Installed Swipe Post accordingly at the center of concrete barrier formwork.


10/2/09 - Formwork and rebar installation for Service Pit (M&E Works) including with 4 Nos. of GI Pipes attached at the both sides.






10/2/09 - Rebar Installation for Concrete Barrier at Toll Island.





7/2/09 - Laid 50 mm and 75mm lean concrete at service pit and concrete barrier area.





7/2/09 - Hacked existing wing wall which is obstruct piling works near box culvert opening.




6/2/09 - Relocated temporary 2 Nos. of street lighting due to subbase backfilling




6/2/09 - Backfilling and recompact subgrade at footing area.





5/2/09 - Carry out PDA Test to the pile at box culvert area.






2/2/09: Reinforcement work for Toll Plaza column in progress.






3/2/09: Box culvert: Setting out piling work.







3/2/09: Fixing pvc rain water down pipe to the column.








3/2/09: Fixing the concrete casing as formwork.






4/2/09: Column concreting in progress.




4/2/09: Piling work at the box culvert area started.