Click to enlarge..
.
.
26/2/09 - Column concreting final level.
26/2/09 - Both highmast completed.
26/2/09 - Installation of Highmast in progress.
25/2/09 - Removing old highmast.
19/2/09 - Concreting swipe post base in progress.
19/2/09 - Fixing swipe post in progress.
17/2/09 - Box culvert area - fixing formwork and river diversion using pipe.
14/2/09 - Construct M&E Manhole.
14/2/09 - Hacked existing concrete pavement for construction joint.
13/2/09 - Divert river flow due to Box Culvert Extension works.
10/2/09 - Formwork and rebar installation for Service Pit (M&E Works) including with 4 Nos. of GI Pipes attached at the both sides.
14/2/09 - Construct M&E Manhole.
14/2/09 - Hacked existing concrete pavement for construction joint.
13/2/09 - Concreting works for 4 nos. of columns upto 2m height column casing.
13/2/09 - Divert river flow due to Box Culvert Extension works.
12/2/09 - Installed 2 Nos of ducts for Fibre Optic and Telecommunication Cables.
12/2/09 - Concreting works
11/2/09 - Installed Swipe Post accordingly at the center of concrete barrier formwork.
12/2/09 - Concreting works
- 800mm depth of Concrete Barriers
- Base for M&E Service Pit
- 2 Nos. of sumps at Pipe Culvert
10/2/09 - Formwork and rebar installation for Service Pit (M&E Works) including with 4 Nos. of GI Pipes attached at the both sides.
10/2/09 - Rebar Installation for Concrete Barrier at Toll Island.
7/2/09 - Laid 50 mm and 75mm lean concrete at service pit and concrete barrier area.
7/2/09 - Hacked existing wing wall which is obstruct piling works near box culvert opening.
6/2/09 - Relocated temporary 2 Nos. of street lighting due to subbase backfilling
6/2/09 - Backfilling and recompact subgrade at footing area.