- Progress Photo - Mar09

28/3/09 - Installation of steel truss



28/3/09 - Excavation for toe drain in progress

27/3/09 - Concreting NJB in progress







26/3/09 - Connecting new fiber optic cable



21/3/09 - Concreting Works for Box Culvert up to Finished Level (Night Work).













20/3/09 - Concreting Works for 3 Nos. of Toll Islands (Night Work).








20/3/09 - Steel trusses welding work in progress












19/3/09 - M&E piping ready for toll booth island.












19/3/09 - Box culvert reinforcement bar erection in progress.







17/3/09 - Transition slab concreting in progress.












12/3/09 - BRC fixing for concrete pavement.











12/3/09 - Water proofing membrane installation in progress.











10/3/09 - Concreting for the 1st concrete pavement in progress (night work).



10/3/09 - Fibre optic cable installation in progress (not urinate!).







6/3/09 - Concreting work for 300 mm x 300 mm box culvert at Toll Booth area.






5/3/09 - Concreting Box Culvert Extension Wall






4/3/09 - M&E Works for Generator Services.