8/1/09: Measuring the depth and area of unsuitable material location near river and box culvert. The box culvert is at left hand side of the photo.
8/1/09: Site clearing works finished.
Ch270: Location where soft ground was found at 1.6m depth from OGL.
Excavating and removing soft ground near ch270.
16/1/09: Ch270 - Carry out Mackintosh Probe at the soft ground area
14/1/09: Backfilling in progress
20/1/09: Backfilling and compaction in progress
22/1/09: Night view - 2 streetlightings involved in relocation work.
22/1/09: Excavation work for toll plaza pad footing in progress.
22/1/09: Toll Plaza pad footing - compacted hardcore
23/1/09: Fixing formworks and erecting reinforcement bars in progress.
23/1/09: Concreting work for all 4 pad footings.
24/1/09: Removing formworks from pad footing.
24/1/09: Compaction work to the side of foundations in progress.